As part of a major project the Ulster Clinic wanted to extend two paring areas out over the edge of an embankment. Hamilton Bogie proposed a design and build solution incorporating top driven mini-piles, ground anchors and a reinforced concrete slab.

The company installed 40 top driven mini piles for vertical support and 20 ground anchors for lateral restraint and also carried out the RC work over a six week period in July and August 2015.